Could P50 Be Your Biggest Hidden Risk in Project Scheduling?
Offshore wind farm construction schedules can fail for one simple reason: teams rely on P50 without understanding what it hides. You can build the most realistic model in the world: š¶Ā Detailed activity sequence, š¶Ā Weather windows & Safe-to-Safe windows, š¶Ā Multiple weather datasets š¶Ā Vessel interactions š¶Ā Port constraintsĀ ā¦and still give your leadership team the āwrongā answer. Imagine they ask ā”Ā āWhen should we charter the vessel to finish before yearāend?ā You run the