Could P50 Be Your Biggest Hidden Risk in Project Scheduling?
- Feb 24
- 2 min read
Offshore wind farm construction schedules can fail for one simple reason: teams rely on P50 without understanding what it hides.
You can build the most realistic model in the world:
đ¶Â Detailed activity sequence,
đ¶Â Weather windows & Safe-to-Safe windows,
đ¶Â Multiple weather datasets
đ¶Â Vessel interactions
đ¶Â Port constraintsÂ
âŠand still give your leadership team the âwrongâ answer.
Imagine they ask âĄÂ âWhen should we charter the vessel to finish before yearâend?â
You run the simulations, look at the results, and select the P50 duration.
 It feels sensible, not too optimistic, not too conservative.
But hereâs the trap: đ50 đšđ§đ„đČ đđđ„đ„đŹ đČđšđź đđĄđ đŠđąđđđ„đ đšđ đđĄđ đđąđŹđđ«đąđđźđđąđšđ§.
 It tells you nothing about the đŹđĄđđ©đ of the risk or the impact of considering only the P50.Â
When we plot project durations using violin plots, the story becomes clearer. (Swipe through the slides)Â
đčMarchâJuly: the distribution is wide around P50 â delays have minimal impact to schedule as range between P10 and P90 is small.Â
đčOctoberâNovember: the distribution narrows around P50 â delays may shift the outcome towards the P90 case.
â¶ In other words:
Your project is likely to finish đđđ«đ„đąđđ« đšđ« đŠđźđđĄ đ„đđđđ« than the P50 suggests.
 And the cost of being late is usually far greater than the benefit of being early.
So perhaps the better question isnâtÂ
âĄÂ âWhen should we charter the vessel to finish before yearâend?â
But instead:Â
âĄÂ "When should we plan to start operation, and what is the impact of less-favourable weather scenarios?"Â
At Scott Marine Consultants, our inâhouse marine modelling software Cicada, powered by offshore engineers, is designed to go beyond raw percentile outputs. We combine realâworld context and real-world operational insights helping teams understand not just what the schedule says but where the real risk sits and what this means for your project.Â














